Title page for ETD etd-12292003-154104


Type of Document Master's Thesis
Author Muthuvelu, Sethumadhavan
Author's Email Address sethu@vt.edu
URN etd-12292003-154104
Title Simultaneous Lot sizing and Lead-time Setting (SLLS)Via Queuing theory and Heuristic search
Degree Master of Science
Department Industrial and Systems Engineering
Advisory Committee
Advisor Name Title
Shewchuk, John P. Committee Chair
Deisenroth, Michael P. Committee Member
Taaffe, Michael R. Committee Member
Keywords
  • MRP
  • lot size
  • planned lead-time
  • MPX
  • queuing theory
  • SLLS
Date of Defense 2003-12-16
Availability unrestricted
Abstract
Materials requirements planning (MRP) is a widely used method for production planning and scheduling. Planned lead-time (PLT) and lot size are two of the input parameters for MRP systems, which determine planned order release dates. Presently, planned lead-time and lot size are estimated using independent methodologies. No existing PLT estimation methods consider factors such as machine breakdown, scrap-rate, etc. Moreover, they do not consider the capacity of a shop, which changes dynamically, because the available capacity at any given time is determined by the loading of the shop at that time. The absence of such factors in calculations leads to a huge lead-time difference between the actual lead-time and PLT, i.e., lead-time error. Altering the size of a lot will have an effect not only on the lead-time of that lot but also on that of other lots. The estimation of lot size and lead-time using independent methodologies currently does not completely capture the inter-dependent nature of lead-time and lot size.

In this research, a lot-sizing model is modified in such a way that it minimizes the combination of setup cost, holding cost and work-in-process cost. This proposed approach embeds an optimization routine, which is based on dynamic programming on a manufacturing system model, which is based on open queuing network theory. Then, it optimizes lot size by using realistic estimates of WIP and the lead-time of different lots simultaneously for single-product, single-level bills of material. Experiments are conducted to compare the performance of the production plans generated by applying both conventional and the proposed methods. The results show that the proposed method has great potential and it can save up to 38% of total cost and minimize lead-time error up to 72%.

Files
  Filename       Size       Approximate Download Time (Hours:Minutes:Seconds) 
 
 28.8 Modem   56K Modem   ISDN (64 Kb)   ISDN (128 Kb)   Higher-speed Access 
  Thesis-Document1.pdf 10.49 Kb 00:00:02 00:00:01 00:00:01 < 00:00:01 < 00:00:01
  Thesis-Document2m.pdf 16.50 Kb 00:00:04 00:00:02 00:00:02 00:00:01 < 00:00:01
  Thesis-Document3.pdf 884.19 Kb 00:04:05 00:02:06 00:01:50 00:00:55 00:00:04

Browse All Available ETDs by ( Author | Department )

dla home
etds imagebase journals news ereserve special collections
virgnia tech home contact dla university libraries

If you have questions or technical problems, please Contact DLA.